6.4.4. Shop Floor Workbench
The Shop Floor Workbench offers enhanced labor tracking and
streamlined Work Order processing for either Operations or Production
posting environments. Its built-in Time Clock functionality ensures precise
run-time reporting. Workbench users are required to clock-in to and
clock-out of Work Orders.
Tip
The clock-in requirement applies only to Shop Floor Workbench users.
If you don"t use the Workbench, no clock-in is required.
Note
This section description includes references to both Operations and
Production posting. Operations posting is only allowed in the OpenMFG
edition of xTuple ERP.
To access the Shop Floor Workbench, select the "Shop Floor Workbench"
option. The following screen will appear:
Note
The Shop Floor Workbench must be configured for either Operations
posting or Production posting. You may not use the Workbench for both
methods simultaneously. To configure the method used by the Shop Floor
Workbench, use the Configure W/O screen in the System module.
When accessing the Shop Floor Workbench, you are presented with the
following options:
- Username
Enter the name of the user wanting to clock-in or clock-out of a
Work Order. Once a username is entered, the display at the bottom of
the screen will show all the Work Orders the user is currently
clocked-in to.
Tip
At the system level, you can restrict a user's privileges so the
Shop Floor Workbench is the only interface they see when they log in to
the application.
- Work Order #
Enter the Work Order Number of the Work Order the user wants to
clock-in to or clock-out of. Only released "R" and in-process "I" Work
Orders may be processed using the Shop Floor Workbench.
Note
A Work Order must be released "R" before users may clock-in or clock
out. The release of a Work Order occurs after the Work Order has been
exploded.
- Whs.
Displays Warehouse code automatically when Work Order Number is
entered into "Work Order #" field.
- Item Number
Displays Item Number automatically when Work Order Number is
entered into "Work Order #" field.
- UOM
Inventory Unit of Measure.
- Status
Displays Work Order Status automatically when Work Order Number
is entered into "Work Order #" field. Only released "R" and in-process
"I" Work Orders may be processed using the Shop Floor
Workbench.
- Operation
If the Workbench is configured for Operations-posting, select an
Operation from the list of Operations. Users are required to clock-in
and clock-out of individual Operations. This allows run-time
calculations to be performed on an Operation-by-Operation basis. A
user may be clocked-in to multiple Operations simultaneously. Also,
multiple users may be clocked-in to the same Operation. Whatever the
case, the run-time clock starts when a user(s) clocks in to an
Operation, and it stops when the user(s) clocks out.
To the far right of the screen, the following buttons are
available:
- CLOSE
Closes the screen without clocking-in or clocking-out, returning
you to the application desktop.
- CLOCK IN
Select to clock-in to the specified Work Order. When a user
clocks-in to a Work Order, the run-time clock starts running from that
point. The clock stops when a user clocks-out of the Work Order. The
elapsed time—or "effort"—is used for labor reporting
purposes. Users may only clock-in to Work Orders they are not already
clocked-in to. However, users may clock-in to and clock-out of the
same Work Order as many times as necessary. Each clock-in starts the
run-time Time Clock; each clock-out stops it.
- CLOCK OUT
Select to clock-out of the specified Work Order. When selected,
the run-time clock stops for the specified Work Order. The time
elapsed since the user last clocked-in is added to the run time total
for the Work Order. This run-time calculation is automatic and cannot
be overridden—except by users who have override privileges.
Users may only clock-out of Work Orders they are already clocked-in
to. If the Workbench is configured for Operations-posting, the "Post
Operations" screen will be presented immediately after the CLOCK OUT
button is selected. By default, the "Scrap Work Order Material from
W/O" screen will immediately follow the "Post Operations"
screen.
Tip
Shop Floor Workbench users should only scrap top-level Items after
they have posted production sufficient to cover the scrap quantity. For
example, if a user assembles 10 top-level Items successfully but
significantly damages the 11th, the user should post a quantity of 11
produced and then scrap one (i.e., 11 - 1 = 10).
- POST PRODUCTION
If the Workbench is configured for Production-posting, the Post
Production screen will be presented immediately after this button is
selected. The button will be hidden if the Workbench is configured for
Operations-posting.
 |
 |
 |
 |