6.3.1. Create W/O Operation
To create a Work Order Operation, select the "Create W/O Operation"
option. The following screen will appear:
When creating a Work Order Operation, you are presented with the
following options:
- Work Order #
Enter the Work Order Number of the Work Order you want to create
an Operation for.
- Whs.
Displays Warehouse code automatically when Work Order Number is
entered into "Work Order #" field.
- Item Number
Displays Item Number automatically when Work Order Number is
entered into "Work Order #" field.
- UOM
Inventory Unit of Measure.
- Oper. Seq. #
Indicates the next available Work Order Operations sequence
number.
-
Execution Day
Select a number using the arrow buttons, or manually enter a
value up to a maximum of 99. (Default is "1".) Value entered defines
when the specified Operation is to begin. For example, if the default
value "1" is entered, the Operation will begin on the first day of the
manufacturing process. If "2" is entered, the Operation will begin on
the second day.
- Qty. Ordered
Displays the quantity ordered for the specified Item.
- Status
Displays Work Order Status automatically when Work Order Number
is entered into "Work Order #" field.
- Standard Oper.
: Select a Standard Operation to be used, if any.
- Description
You will notice that two separate description fields are
available here. This makes it possible to isolate different categories
of information onto separate lines. For example, the first line might
contain an Item name, while the second line contains packaging
information. Having these two types of information one above the other
can serve as a kind of useful shorthand when viewing data in certain
windows. However, these two lines will be concatenated (i.e., "joined
together") when they are printed or presented in an on-line display
format.
- Work Center
Specify a Work Center to be used for specified Operation.
-
Production UOM
Select a Unit of Measure—or enter a free-form UOM. Specify a
UOM to be used optionally when Work Order Operations are posted for
the specified Operation. Operations may be posted using either the
Inventory or Production UOM. In addition, different Operations in a
single Bill of Operations may use different Production UOMs. For
example, if you are producing soup, you might mix the soup in one
Operation using UOM = BATCH. But when canning the soup, the canning
Operation might use UOM = CAN. If you post Operations using the
Production UOM, the Inventory/Production UOM ratio normalizes the
posting so that the Inventory impact is recorded using the Inventory
UOM.
Note
When posting Work Order Operations, you are given the option to post
Operations using Production UOMs or Inventory UOMs.
- Inventory/Production UOM Ratio
When Work Order Operations are posted using the Production UOM,
the Inventory/Production UOM ratio normalizes the posting so that the
Inventory impact is recorded in the Inventory UOM.
- Tooling Reference
Enter a tooling reference—if applicable.
Note
Labor and overhead Costs associated with setup and run times must be
reported if they are to be tracked in the G/L and elsewhere. To report
setup and run times, select the appropriate boxes in the Operation
screen.
-
Total Setup Time
Setup Time: Amount entered represents the number of minutes
required to set up the Work Center for the Operation.
- Report Setup Time
-
Select to report setup time.
Must be selected for labor Costs associated with setup to be
tracked in the G/L and elsewhere. If not selected, these Costs will
not be reported.
-
Total Run Time
Run Time: Amount entered represents the total run time for the
Operation measured in minutes.
- Report Run Time
Select to report run time. Must be selected for labor Costs
associated with run time to be tracked in the G/L and elsewhere. If
not selected, these Costs will not be reported.
- Throughput
Indicates the number of units, in the given Item's Inventory
UOM, that can be produced in a minute—and also the number of minutes
that are required to produce 1 unit, expressed in the given Item's
Inventory UOM.
- Receive to Stock at this Operation
Select if you want finished goods to be received into Inventory
when this Operation is posted. Only one Work Order Operation may have
this flag set. If this option is selected, the General Ledger will
show the finished goods being received into Inventory when the
Operation is posted.
- Auto. Issue Components at this Operation
Select if you want linked component material to be issued
automatically (i.e., backflushed) when this Operation is posted. If
this option is selected, the General Ledger will show the component
materials being removed from Inventory when this Operation is
posted.
Note
The "Auto. Issue" setting applies only to component Items whose
issue method is either "Pull" or "Mixed". Component Items using the "Push"
issue method must be issued to Work Orders using a specific material issue
transaction.
- Setup Time Consumed
Displays setup time consumed.
- Run Time Consumed
Displays run time consumed.
- Setup Time Remaining
Displays setup time remaining.
- Run Time Remaining
Displays run time remaining.
- Setup Complete
Selected if setup complete.
- Run Complete
Selected if run complete.
- Instructions
This is a scrolling text field with word-wrapping for entering
instructions related to the Operation.
- Use Fixed-Width Font
Select to display text in the "Instructions" field in
fixed-width font. This is a useful feature for displaying tables,
matrixes, and other format-driven texts.
Note
If copying formatted text from another application, formats may
translate imperfectly.
To the far right of the screen, the following buttons are
available:
- CANCEL
Closes the screen without creating the Work Order Operation,
returning you to the application desktop.
- SAVE
Creates the Work Order Operation.
|
 |
 |
 |