Run MRP section. When you run MRP by Planner Code, you are running the Material Requirements Planning (MRP) system. This utility creates Planned Replenishment Orders to meet existing Sales Order and Work Order demand. Replenishment Orders will be created whenever a Planned Availability for an Item Site falls below its Reorder Level. The quantity of the Replenishment Order will be enough to restore Planned Availability back to the Reorder Level—or to the Order Up To (OUT) Level, if the OUT Level is greater. NoteRunning MRP by Planner Code may be used to generate Planned Orders for both parent-level manufactured Items and also lower level purchased Items. Only Items designated as MRP Items will be affected by an MRP run. To run MRP by Planner Code, select the "Run MRP by Planner Code" option. The following screen will appear:
![]() Run MRP by Planner Code
NoteThe system deletes any non-firmed Planned Orders when MRP is run. If demand for the deleted Planned Orders still exists, the Orders will be replaced by new Replenishment Orders having new Planned Order Numbers. Order quantities will also be updated if demand levels have changed since MRP was last run. When running MRP by Planner Code, you are presented with the following options:
TipIf you schedule an MRP or MPS job submitted to the Batch Manager to run on a periodic basis—daily, weekly, monthly—the cutoff date used for the run will automatically be updated by the number of days in the specified reschedule interval (Day = +1, Week = +7, and Month = +30).
TipUnposted Purchase Orders and Purchase Requests are considered as valid sources of supply when MRP is run. To the far right of the screen, the following buttons are available:
When you run MRP by Item, you are running the Material Requirements Planning (MRP) system. This utility creates Planned Replenishment Orders to meet existing Sales Order and Work Order demand. Replenishment Orders will be created whenever a Planned Availability for an Item Site falls below its Reorder Level. The quantity of the Replenishment Order will be enough to restore Planned Availability back to the Reorder Level—or to the Order Up To (OUT) Level, if the OUT Level is greater. TipWhen running MRP by Item for manufactured Items, the system generates Planned Work Orders only. If you want to also generate Planned Orders for purchased requirements, you should run MRP by Planner Code. Only Items designated as MRP Items will be affected by an MRP run. To run MRP for an individual Item, select the "Run MRP by Item" option. The following screen will appear:
![]() Run MRP by Item
NoteThe system deletes any non-firmed Planned Orders when MRP is run. If demand for the deleted Planned Orders still exists, the Orders will be replaced by new Replenishment Orders having new Planned Order Numbers. Order quantities will also be updated if demand levels have changed since MRP was last run. When running MRP by Item, you are presented with the following options:
TipUnposted Purchase Orders and Purchase Requests are considered as valid sources of supply when MRP is run. To the far right of the screen, the following buttons are available:
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||