xTuple Solutions About Us Resources News
Our Products

More Open Source
 OpenRPT report writer
 PostgreSQL database
 Pricing for all services

Our Community
 xTuple.org Home
 Forums & Mail
 Issue/Bug Tracker
 Search xTuple.org
 Downloads

Industry case studies
 Automotive aftermarket
 Bearings and pulleys
 Fresh/frozen foods
 Garments (make to order)
 Inks and ink technology
 Pumps and valves
  - View all case studies

Free Demo Download
 Please login:
username:
password:
 ... or click here to register:

  ... End Users
  ... Solution Providers

4.1. Production Plan

The Master Production Scheduling (MPS) system serves several important purposes:

  1. Increases visibility into future demand

  2. Provides capability for anticipating future demand

  3. Drives the plan for lower level components (i.e., Material Requirements) based on the Forecast

Production Plans are at the heart of MPS. Using Production Plans, you have the ability to load sales Forecasts into the system—and then view the impact of the Forecasts on production planning.

Typically, MPS is used to plan for Items having "independent" demand. Independent demand Items are defined as those Items which derive their demand directly from Customer requirements through Sales Orders. By contrast, "dependent" demand Items are normally purchased Items and subassemblies. The demand for dependent Items is derived indirectly—that is, based on the demand for their parent Items in a Bill of Materials. The Material Requirements Planning (MRP) system is typically used to plan for dependent demand.


 