3.9.3. Topic: Order Parameters and MRP xTuple :
xTuple Logo Solutions About Us Resources News

Our Products
xTuple Open Source ERP Products
PostBooks
Standard Edition
OpenMFG Edition

More Open Source
 OpenRPT Report Writer
 PostgreSQL Database
 Pricing for all services


xTuple ERP 3.0 won the LinuxWorld product excellence award for best Business Application! Read more here!

Our Community
 xTuple.org Home
 Forums & Mail
 Issue/Bug Tracker
 Search xTuple.org
 Downloads

Industry case studies
 Automotive aftermarket
 Bearings and pulleys
 Fresh/frozen foods
 Garments (make to order)
 Inks and ink technology
 Pumps and valves
  - View all case studies

Free Demo Download
 Please login:
username:
password:
 ... or click here to register:

  ... End Users
  ... Solution Providers

3.9.3. Topic: Order Parameters and MRP

This section is designed to briefly illustrate the interaction between Order Parameters and Material Requirements Planning (MRP). As you will see, Order Parameters play a key role in the execution of MRP.

3.9.3.1.  Item Site Settings

For the purposes of this exercise, we will be looking at the Order Parameter settings for a purchased Item—Item V1. The following screenshot shows the Item Site master for Item V1:

Item Site with Order Parameters Selected

As you can see in the example, the "Enforce Order Parameters" flag is set for this Item Site. Selecting this option tells the system to enforce the specified Order Parameters when MRP is run. The "on Manual Orders" option applies to manual Work Orders only and does not have an impact on MRP.

Let's define the significance of each Order Parameter setting:

  • Reorder Level: Specifies when a Planned Replenishment Order should be created for an Item Site. If Planned Availability minus Safety Stock falls below the Reorder Level, then a Replenishment Order will be created when MRP is run. The Replenishment Order quantity will be equal to the quantity required to return Planned Availability to either the Reorder Level or the Order Up To quantity—whichever is greater. We will look at Planned Availability later in this section. In this example, the Reorder Level is set to 30. So, when Planned Availability minus Safety Stock falls below 30, MRP (when it is run) will recognize this and reorder quantities for the Item Site.

  • Order Up To: Indicates the level of Planned Availability an Item Site should be replenished up to when MRP is run. In cases where the Reorder Level for an Item Site exceeds the Order Up To (OUT), MRP will replenish the Item Site up to the Reorder Level. In this example, the OUT Level is 100. So, in our example, when Planned Availability falls below the Reorder Level, MRP (when it is run) will replenish the Item Site quantity up to 100.

Tip

Setting the Order Up To Level to "0" removes any restrictions on maximum Order quantities. Removing quantity restrictions can be an effective strategy to help ensure that all Order demands are satisfied when MRP is run. Order demands may not be met if Order Up To Levels are set below the demand threshold.

  • Minimum Order: Indicates the minimum quantity that may be entered for a Planned Replenishment Order when MRP is run. In this example, no minimum Order quantity is specified.

  • Order Multiple: Indicates the quantity multiple that should be used for Planned Replenishment Orders when MRP is run. In this example, the Order multiple = 1.

  • Group MRP Orders Every: Value entered specifies the length of a period—measured in days—within which Planned Replenishment Orders will be grouped together (i.e, consolidated) to meet scheduled demand for the period. This functionality serves to limit the total number of Planned Replenishment Orders, thereby simplifying order processing. For example, to consolidate demand for an Item Site into 30-day buckets, set the value to "30." When MRP is run, the system will automatically consolidate all demand falling within the 30-day horizon into a single Planned Purchase Order or Planned Work Order. The grouping of Planned Orders moves forward in time, meaning the system will create as many buckets as will fit within the cutoff date specified when MRP is run. The initial grouping of Planned Orders is handled differently than subsequent buckets. The following formula specifies how the date range for the initial period is determined:

    Start Date = Today's Date

    End Date = Today's Date + Lead Time

    All subsequent periods are determined using the following calculations:

    Start Date = End Date of Previous Period + 1

    End Date = Start Date of Current Period + Group Value

Tip

To enforce Just-In-Time (JIT) delivery methods, set the MRP group value to "0." This will ensure that Planned Order due dates are the same as the demand due dates to which they correspond. If the MRP Order grouping value is set to "0", the initial period will be determined in the same way as for all Planned Order groups:

Start Date = Today's Date

End Date = Today's Date + Lead Time

However, the date range for all subsequent JIT Planned Orders will be based on the following calculations:

Start Date = Demand Due Date - Lead Time

End Date = Demand Due Date

  • Safety Stock: Specifies the quantity of Stock you want to keep in Inventory to protect against unplanned, unforeseeable trends in your Order forecasts. When Material Requirements Planning (MRP) is run, the system considers the Safety Stock value when determining whether to create Planned Replenishment Orders. If Planned Availability minus Safety Stock is below the Reorder Level, then Planned Orders will be created. If not below the Reorder Level, then no Planned Orders will be created. The system's calculation effectively creates a buffer Inventory (if needed) to handle unexpected fluctuations in demand. In this example, Safety Stock is set to 20.

Tip

If you do not want to use the Safety Stock functionality, set the Safety Stock value to "0".

3.9.3.2. Viewing Planned Availability

Planned Availability—also known as available quantity—describes Inventory quantity available for consumption by Work Orders or Sales Orders. To determine available quantity, the system uses the following formula:

  • Planned Availability = Unallocated Qty. + Qty. on Order

Let's look now at Planned Availability for Item V1. The Inventory Availability by Item screen found in the I/M Module provides us with this detail, as shown below:

Inventory Availability Display Showing Availability Below Reorder Level

As you can see from the screenshot, the available quantity is displayed in orange. The orange-colored font is used to indicate that Planned Availability has fallen below the Reorder Level. Whenever this scenario occurs, Planned Replenishment Orders will be generated the next time MRP is run.

The following columns are of interest to us now:

  • QOH = 25: In this example, the Quantity on Hand (QOH) is equal to the available quantity. If quantities of Item V1 were in any way allocated, these two values would not be the same.

  • Allocated = 0: Item quantity is considered allocated if Sales Orders or Work Orders are demanding the Item. In this case, no outstanding demands for Item V1 have been created in the system, and so the allocated quantity = 0.

  • Unallocated = 25: Because Item V1 is not currently allocated to any Sales Orders or Work Orders, the unallocated quantity equals the QOH.

  • Reorder Lvl. = 30: This is the Reorder Level specified on the Item Site definition.

  • OUT Level = 100: This is the Order Up To Level specified on the Item Site definition.

  • Available = 25: Doing some simple math, you can see that the available quantity of Item V1 in Warehouse EAST is below the Reorder Level--5 units below it, in fact. As a result, a Planned Replenishment Order for Item V1 should be created when MRP is run.

3.9.3.3. Running MRP

Now let's run MRP and see what happens. Based on our knowledge of the Item Site Order Parameters and the available quantity for Item V1, we know that a Planned Replenishment Order will be created. We know this because the following condition is true:

Planned Availability (25) - Safety Stock (20) < Reorder Level (30).

Whenever Planned Availability minus Safety Stock falls below the Reorder Level, a Planned Order will be generated when MRP is run. The only question now is what will the Planned Order quantity be?

The following M/S Module screen, "Run MRP by Item," is one of two utilities used to run MRP—the other is "Run MRP by Planner Code." For this exercise, we will be running MRP by Item, as shown in the following screenshot:

Running MRP by Item

We enter Item V1 in the Item Number field, specify the Warehouse where the Item Site is located, and set the Cutoff Date for the current day. Once we select the CREATE button, MRP is off and running. To see the resulting Planned Replenishment Orders, we open the M/S Display "Planned Orders by Item," as shown in the following screen:

MRP Created Planned Purchase Order

As you can see in the example, a Planned Purchase Order has been generated for 75 units of Item V1. So how did the system determine that 75 units was the required quantity?

Well, when MRP creates Planned Orders, the system looks at both the Reorder Level and the Order Up To (OUT) Level. It determines which of the two has the greater value—and then it places an Order to replenish available quantity up to that value. In our example, the OUT Level (100) is the greater value. And so we have the following scenario:

25 (Current Available Qty.) + 75 (Needed Replenishment Qty.) = 100 (OUT Level)

So you can see, MRP generated a Planned Order for 75 units of Item V1 to restore available quantity to the OUT Level.

Note

Because Item V1 is a purchased Item, the Replenishment Order is a Planned Purchase Order. Had the Item been a manufactured Item, Planned Work Orders would have been created—and also Planned Purchase Orders, depending on the availability and Reorder Levels of required component Items.

3.9.3.4.  Converting Planned Orders to Actual Orders

The next step is to convert the Planned Purchase Order to a Purchase Request. Doing so will make Purchasing aware of the requirement. We can release the Order using the "Release Order" option from the right-click menu. After choosing that option, we are prompted to create a Purchase Request, as shown below:

Convert Planned Order to Purchase Request

A quick check of the details on the "Purchase Request" screen shows us that the quantity ordered is correct. We now select the CREATE button to generate the Purchase Request and forward it to Purchasing. To verify this activity, we turn to the P/O Module Display Purchase Requests by Item, as shown below:

Release Purchase Request

Sure enough, there's the Purchase Request for the correct quantity. Once again, we select the "Release Order" option from the right-click menu. Because Item Sources have been defined for the Item, we are asked to pick a Vendor from among the list of possible Vendors for this Item, as shown in the next screen:

Select Item Source during Purchase Request Conversion

We choose the Vendor Smithson Industries from the list, because this is the Vendor with the highest ranking. After selecting the Vendor, we are asked whether we want to add the Item to an existing open Purchase Order—or whether we would like to create a new Purchase Order for this Item:

Choose Existing or New PO

After making our choice, we are brought straight to the Purchase Order Line Item screen. As you can see in the next screenshot, all the correct values have automatically been entered: Item Number, Order quantity, unit price, extended price, due date, etc.:

P/O Line Item with Values Pre-Populated

We verify the details and then select the SAVE button. Finally we are brought to the Purchase Order header, as shown below:

Purchase Order Originated by MRP Replenishment

As you can see, we have successfully created a Purchase Order using MRP replenishment functionality. All we have to do now is post the Purchase Order, and the replenishment quantity will be well on its way.



 