An Item Site identifies and defines the methods and controls used when
maintaining a given Item within a given Warehouse. To enter a new Item Site
into your system, select the "Enter Item Site" option. The following screen
will appear:
When creating a new Item Site, you are presented with the following
options:
- Item Number
Enter the Item Number of the Item you want to create an Item
Site for.
- UOM
Inventory Unit of Measure.
- Active
Select to indicate the Item Site is active. Not selecting means
the Item Site will be considered inactive. If inactive, the Item Site
will not appear on lists of active Item Sites. To re-activate an Item
Site, simply select this option.
- Warehouse
Specify Warehouse where Item Site is located. Use this selection
in conjunction with the additional Warehouse settings found on the
Item Site screen.
- Supplied at this Warehouse
Select if Item is supplied at specified Warehouse. If selected,
"Supplied at" means that Purchase Orders may be issued for this Item
in this Warehouse if the Item is a purchased Item, and Work Orders may
be issued for this Item in this Warehouse if the Item is a
manufactured Item. These rules apply also to Planned Orders generated
when Material Requirements Planning (MRP) is run. Planned Orders may
only be released to "Supplied at" Item Sites.
- Create P/Rs to Meet Demands
Select to create Purchase Requests whenever Sales Orders or Work
Orders demand quantities from the Item Site. This option pertains to
purchased and outside-process Items. If you select this option, you
are indicating that you want Purchase Requests to be generated for the
Item in question whenever quantities are demanded by either Sales
Orders or Work Orders. For Sales Orders, the "Create Purchase Request"
flag on the Sales Order Item screen will automatically be selected.
For Work Orders using a purchased or outside process Item, Purchase
Requests will be generated automatically.
Note
Purchase Requests created, as specified above, to meet Sales Order
and Work Order demands will be created regardless of an Item's
Availability—and also regardless of whether Material Requirements
Planning (MRP) is being run in parallel.
- Create W/Os to Meet Demand
Select to create Work Orders whenever Sales Orders demand
quantities from the Item Site. This option pertains to manufactured
Items. If you select this option, you are indicating that you want
Work Orders to be generated for the Item in question whenever
quantities are demanded by a Sales Order. Selecting this option will
cause the "Create Work Order" flag to be checked whenever you enter
Sales Order Line Items for the Item Site.
Note
Work Orders created, as specified above, to meet Sales Order demand
will be created regardless of an Item's Availability—and also regardless
of whether Material Requirements Planning (MRP) is being run in
parallel.
- Sold from this Warehouse
Select if Item is sold from specified Warehouse. If selected,
"Sold from" means that Sales Orders Line Items may request to Ship
from the Warehouse. When adding Sales Order Line Items to a Sales
Order, a "Sold from" Warehouse appears as the "Supplying
Warehouse."
- Ranking
Select a number using the arrow buttons, or manually enter a
value up to a maximum of 10. Value entered specifies the order in
which Item Sites will be chosen during Sales Order and Sales Quote
creation. If an Item is located in more than one "Sold from"
Warehouse, the Item Site with the highest ranking will be chosen
first. If two Item Sites happen to share the same ranking, selection
will be based on alphabetical order. The highest ranking an Item Site
can have is one (1).
- Control Method
-
Specify the Item Site control method by selecting one of the
available options:
- None
Select if you don"t care to see Inventory history
transactions for the Item Site.
- Regular
Select to monitor Inventory history transactions for the
Item Site using a Regular method. Regular means without Lot
Number or Serial Number control.
- Lot #
Select to impose Lot Number control methods on the Item
Site. Item Sites using Lot Number control are subject to unique
processing requirements whenever Inventory is received or
distributed. For additional information on some of the unique
methods required to handle Lot-controlled Items, see Section 3.5.6, “Topic: Receiving Lot/Serial Items into
Inventory”.
- Serial #
Select to impose Serial Number control methods on the Item
Site. Item Sites using Serial Number control are subject to
unique processing requirements whenever Inventory is received or
distributed. For additional information on some of the unique
methods required to handle Serial-controlled Items, see Section 3.5.6, “Topic: Receiving Lot/Serial Items into
Inventory”.
- Perishable
Select if the Item is perishable. For Item Sites whose control
method is either Lot Number or Serial Number, you have the option of
also designating the Item Site as Perishable. Materials received into
a Perishable Item Site are required to specify an expiration date,
thereby increasing your ability to monitor the status of the
goods.
- Planner Code
Specify the Planner Code you want to assign the Item Site to.
Assigning a Planner Code to an Item Site makes it possible to group
Item Sites by Planner Code for the purposes of Planning.
- Cost Category
Specify the Cost Category you want to associate with the Item
Site. Item Sites must be assigned a Cost Category. This requirement
helps ensure that all Inventory transactions involving an Item Site
will be properly tracked and recorded in the General Ledger.
- Multiple Location Control
Select if the specified Item is to be stored in multiple
Locations within a single Warehouse. Items designated as Multiple
Location Control (MLC) Items require special processing whenever Item
quantities are distributed. For more information on distributing MLC
Item quantities, see Section 3.5.2, “ Topic: Distributing Multiple Location Control (MLC)
Items”.
Tip
Exercise caution when adjusting the Multiple Location Control (MLC)
setting for an Item Site. If you turn off MLC for an Item Site which was
previously MLC, you will lose detailed Inventory records for that Item
Site. All quantity will be merged into one Quantity on Hand value for the
Item Site.
- Use Default Location
Default Location: Select to designate one Location within a
Warehouse as the default Location for the specified Item. This option
may be used for single Location and Multiple Location Control (MLC)
Items alike. You may find that Inventory distributions for MLC Items
are greatly simplified if you designate a default Location.
- Location
Specify the Warehouse Location to be used as the default
Location.
- User-Defined
This is a free-form field for describing storage areas with a
Warehouse not specifically designated as Warehouse Locations.
- Location Comment
Enter any free-form Comment related to the Warehouse Location.
This is additional information which may be placed on a Pick List or a
Pack List.
- Disallow Blank WIP Locations
Select to require the use of work-in-process (WIP) Locations
when posting Work Order Operations for Multiple Location Control (MLC)
finished goods. WIP Locations are an optional feature which may be
defined on the Bill of Operations (BOO) for manufactured MLC Items.
The feature enables you to track finished goods Inventory as it moves
through the manufacturing process. If your site does not combine
Multiple Location Control with Operations posting, then this option
should be left unchecked.
- Stocked
Select if the Item is stocked at the specified Warehouse. This
setting is used to drive the constraint management system. As a
result, to avoid inaccurate results when running that system, an Item
Site must also have a Reorder Level defined to use this option.
- ABC Class
-
Specify the ABC classification for the specified Item.
- Allow Automatic Updates
Select to allow the ABC Class setting for the Item Site to
be updated whenever the ABC Class update utility is run. Not
selecting indicates the ABC Class for the Item Site should not
be updated whenever the ABC Class update utility is run.
- Cycl. Cnt. Freq.
Cnt. Freq.: Select a number using the arrow buttons, or manually
enter a value up to a maximum of 999. A Cycle Count is a periodic
issue of a Count Tag to count Inventory quantity within an Item Site.
The Cycle Count frequency defines the length of that period, measured
in days.
Tip
To monitor the frequency of Item Site Cycle Counts, view the "Last
Counted" column in any of the Item Site Reports: by Item, by Class Code,
etc. The Last Counted date represents the date a Count Tag was last posted
(not simply issued) for the Item Site.
- Event Fence
Select a number using the arrow buttons, or manually enter a
value up to a maximum of 99. Specify the period of time, measured in
days, within which relevant Event notifications should be issued. If
an Event affecting the Item Site occurs within the Event Fence, then
the system will issue a notification. Consider the case of a
manufactured Item whose Event Fence is set to five (5) days. Assume
that a Work Order exists for this Item and that the scheduled start
date for that Work Order is three (3) days from the current date. If
someone were to change the quantity of that Work Order, the Event
"WoQtyChanged" would be triggered. And because the Work Order start
date falls within the Event Fence for the Item Site, an Event
notification would be issued.
To the far right of the screen, the following buttons are
available:
- CANCEL
Closes the screen without creating an Item Site, returning you
to the application desktop.
- SAVE
Creates the Item Site and adds it to the master list of Item
Sites.
To set the Item Site planning parameters, select the "Planning" tab.
The following screen will appear:
When setting the Item Site planning parameters, you are
presented with the following options:
- Enforce Order Parameters
-
Order Parameters: Select to enforce Order Parameters.
If this option is selected, then Material Requirements Planning
(MRP) will follow the Order Parameters defined below when generating
Planned Replenishment Orders. Parameters you define will be saved if
this option is turned ON/OFF. If you want to enforce Order Parameters
on manual Orders as well, select the "on Manual Orders" option. For
more information on how Order Parameters interact with MRP, see Section 3.9.3, “Topic: Order Parameters and MRP”.
Note
Running Material Requirements Planning (MRP) on your system consists
entirely of running the Create Planned Replenishment Orders
screens—either by Item or by Planner Code. As MRP runs, the Planned
Replenishment Orders are generated automatically.
- Reorder Level
The Reorder Level specifies when a Planned Replenishment Order
should be created for an Item Site. If Planned Availability minus
Safety Stock falls below the Reorder Level, then a Replenishment Order
will be created when Material Requirements Planning (MRP) is run. The
Replenishment Order quantity will be equal to the quantity required to
return Planned Availability to either the Reorder Level or the Order
Up To quantity—whichever is greater. For more information, see Section 3.9.3, “Topic: Order Parameters and MRP”.
Note
Planned Availability differs from Quantity on Hand (QOH). The
difference is that Planned Availability considers both QOH and also the
time-phased demands placed on Inventory by Sales Orders and Work Orders.
MRP uses Planned Availability when calculating which Item Sites require
Planned Replenishment Orders.
- Order Up To
The Order Up To (OUT) Level indicates the level of Planned
Availability an Item Site should be replenished up to when Material
Requirements Planning (MRP) is run. In cases where the Reorder Level
for an Item Site exceeds the Order Up To Level, MRP will replenish the
Item Site up to the Reorder Level. For more information, see Section 3.9.3, “Topic: Order Parameters and MRP”.
Tip
Setting the Order Up To Level to "0" removes any restrictions on
maximum Order quantities. Removing quantity restrictions can be an
effective strategy to help ensure that all Order demands are satisfied
when MRP is run. Order demands may not be met if Order Up To Levels are
set below the demand threshold.
- Minimum Order
Value entered indicates the minimum quantity that may be entered
for a Planned Replenishment Order when MRP is run. If the "on Manual
Orders" option is selected above, manually-created Work Orders will
recognize the Minimum Order value.
- Maximum Order
This is a special setting which regulates the maximum quantity
for Planned Replenishment Orders when MRP is run. The setting does not
apply to manual Orders, but to Planned Orders only. When a maximum
Order quantity is specified, MRP will ignore Order multiples and
minimum Order specifications—focusing instead solely on the maximum
Order setting. For example, if the maximum Order quantity is set to 10
and there is demand for 17, then Planned Orders of 10 and 7 would be
generated when MRP is run.
Tip
Setting the maximum order quantity too low has been shown to slow
performance when MRP is run. Unless you have special needs (i.e., crate
packaging limits) which require you to set a low maximum order quantity,
you should consider setting the maximum order value to "0".
- Order Multiple
Value entered indicates the quantity multiple that should be
used for Planned Replenishment Orders when MRP is run. If the "on
Manual Orders" option is selected above, manually-created Work Orders
will recognize the Order Multiple value.
- Enforce on Manual Orders
Select to enforce Order Parameters on manually-created Work
Orders. If this option is selected, Order Parameters will also be
enforced whenever Work Orders are manually created. This option
applies only to the following two parameters: Minimum Order and Order
Multiple. The other Order Parameters listed below do not apply to
manually-created Work Orders. For manual Purchase Orders, the Minimum
Order and Order Multiple parameters are determined on a
Vendor-by-Vendor basis, using Item Source masters.
- Group MPS/MRP Orders Every
-
Specify the length of a period—measured in days—within which MPS
or MRP Planned Orders will be grouped together (i.e, consolidated) to
meet scheduled demand for the period. This functionality serves to
limit the total number of Planned Orders, thereby simplifying order
processing. For example, to consolidate demand for an Item Site into
30-day buckets, set the value to "30." When MRP is run, the system
will automatically consolidate all demand falling within the 30-day
horizon into a single Planned Purchase Order or Planned Work Order.
The grouping of Planned Orders moves forward in time, meaning the
system will create as many buckets as will fit within the cutoff date
specified when MRP is run.
The initial grouping of Planned Orders is handled differently
than subsequent buckets. The following formula specifies how the date
range for the initial period is determined:
Tip
To enforce Just-In-Time (JIT) delivery methods, set the MRP group value
to "0." This will ensure that Planned Order due dates are the same as the
demand due dates to which they correspond. If the MRP Order grouping value
is set to "0", the initial period will be determined in the same way as
for all Planned Order groups:
However, the date range for all subsequent JIT Planned Orders will
be based on the following calculations:
- MPS Time Fence
Specify the length of the Demand Time Fence by using the arrow
buttons or manually entering a value up to a maximum of 999. The
Demand Time Fence (also known as the demand fence) is used by the
Master Production Scheduling (MPS) system to evaluate when forecasted
demand (i.e., from Production Plans) should be used in place of actual
demand (i.e., from Sales Orders)--and vice versa. Measured in days,
the Demand Time Fence is the period of time extending from the current
day to the number of days into the future as specified in this field.
The Demand Time Fence option applies only to those Items which
currently appear on a released Production Plan. If demand for these
Items falls within the Demand Time Fence period, then the Forecast
will be ignored. If demand falls outside the Demand Time Fence, then
the larger of actual or forecasted demand will be used. MPS responds
to the demand it locates by creating firm Planned Orders for the
required quantities.
- Lead Time
Select a number using the arrow buttons, or manually enter a
value up to a maximum of 999. Specifies the Lead Time for the
specified Item, measured in days. If the Item is a manufactured Item,
then the Lead Time refers to the production Lead Time. If the Item is
a purchased Item, then the Lead Time refers to the planning Lead Time.
The procurement Lead Time for purchased Items is determined on a
Vendor-by-Vendor basis, using Item Source masters. Material
Requirements Planning (MRP) will consider Lead Times when calculating
Planned Order start dates when MRP is run.
- Safety Stock
Specify the quantity of Stock for the Item you want to keep in
Inventory to protect against unplanned, unforeseeable trends in your
Order forecasts. When Material Requirements Planning (MRP) is run, the
system considers the Safety Stock value when determining whether to
create Planned Replenishment Orders. If Planned Availability minus
Safety Stock is below the Reorder Level, then Planned Orders will be
created. If not below the Reorder Level, then no Planned Orders will
be created. The system's calculation effectively creates a buffer
Inventory (if needed) to handle unexpected fluctuations in demand. If
you do not want to use the Safety Stock functionality, set the Safety
Stock value to "0".
To add miscellaneous Notes to an Item Site, select the "Notes" tab.
The following screen will appear:
- Notes
This is a scrolling text field with word-wrapping for entering
free-form Notes related to the Item Site. Notes differ from Comments
in that Comments are time/date and user stamped.
To associate Comments with an Item Site, select the "Comments" tab.
The following screen will appear:
- Comments
Display lists the date Comment entered, Comment Type, user who
entered Comment, and a content preview.
To the far right of the screen, the following buttons are
available:
- NEW
Opens screen for creating a new Comment.
- VIEW
Highlight a Comment and then select this button to reach a
read-only view of the Comment.
To create a new Comment, select the NEW button. The following screen
will appear:
- Comment Type
Specify one of the following Comment Types from the drop-down
list: ChangeLog or General. Comment Types are used to categorize
Comments. Once you have specified a Comment Type, you may type your
Comment in the main text area. The text area features word-wrapping
and scroll-bar support for longer Comments.
To the far right of the screen, the following buttons are
available:
- CANCEL
Closes the screen without creating the Comment, returning you to
the previous screen.
- SAVE
Creates the Comment and adds it to the list of Comments.
Warehouse Locations may be restricted to allow for storage of
certain Items. To view restricted Locations within an Item Site's Warehouse,
select the "Restricted Locations" tab. The following screen will
appear:
The Restricted Locations list will show restricted Locations
associated with the Warehouse the Item Site is located in.
To the far right of the screen, the following buttons are
available:
- TOGGLE
Highlight a Warehouse Location and then select this button to
change the allowed status for the Item. Any changes made on the Item
Site master related to an Item's allowed status will also be saved to
the Warehouse Location master record.
|
 |
 |